MDS has packed up and no longer has a presence in Lytton pre se. We are doing some small tasks as we get closer to the final inspection, which allows occupation by the Coghlan family. The western maple countertop was installed on the 14th, and the sinks and taps were scheduled to be completed this week (ending August 22nd).

The dedication will likely proceed sometime in the first half of September.

Adeline and Duane are scheduled to start providing leadership in Barrington, Nova Scotia, beginning August 28 through to September 26 on a new build for an elderly gentleman who lost his home in the 2023 fire in NS.